ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
29INR0251 · Solar · Kinney County

Sugarberry Solar SLF

Sugarberry Solar SLF is a 125 MW solar project in Kinney County, Texas, connecting at 78255 Pinto Creek 138 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/18/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
29INR0251
Capacity
125 MW
Fuel
Solar (PV)
Interconnecting entity
EG Sugarberry LLC
Projected COD
12/18/2029
Entered queue
02/12/2026
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 02/12/2026
    Entered the queue with 125 MW, projected COD 12/18/2029
  • 02/12/2026
    Screening → FIS Requested

Other projects at this substation

Sugarberry Storage SLFBESS0 MWFIS Requested