25INR0501 · Solar · Kinney County
Longday Solar SLF
Longday Solar SLF is a 201 MW solar project in Kinney County, Texas, connecting at Tap138 kV 8252 Brackettville - 8260 Escondido. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/15/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0501
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- County
- Kinney County
- Interconnecting entity
- Longday Solar
- Projected COD
- 12/15/2027
- Entered queue
- 07/20/2023
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 07/20/2023Entered the queue with 201 MW, projected COD 12/15/2027
- 07/20/2023Screening → FIS Requested
Other projects at this substation
No other projects at this substation.