LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0541 · BESS · Kinney County

Kinney County Energy

Kinney County Energy is a 101 MW battery storage project in Kinney County, Texas, connecting at Tap 138kV 8252 Brackett4A - 78255 L_PINTCR8_1Y. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 05/15/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0541
Capacity
101 MW
Fuel
BESS (BA)
Interconnecting entity
Kinney County Energy, LLC
Projected COD
05/15/2027
Entered queue
03/27/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/24/2023
    Screening → FIS Requested
  • 03/27/2023
    Entered the queue with 101 MW, projected COD 05/15/2027

Other projects at this substation

No other projects at this substation.