LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Fort Bend County power projects

Fort Bend County, Texas has 11 active power projects totalling 2,008 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,008 MW (100%). The largest single project is Avalon BESS (522 MW battery storage). 5 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
11
2.0 GW capacity
IA signed or later
5
45% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
3
since Sep 2026

Changes in Fort Bend County

COD change
10/01/2026
IEP Orchard BESS · BESS · Fort Bend County
Projected COD moved 09/18/2026 → 12/31/2027. Delay #1 for this project.
+15 mo
Withdrawn
09/14/2026
Creekfield Solar · Solar · Fort Bend County
Listed as cancelled by ERCOT.
−161 MW
Withdrawn
09/14/2026
Creekfield Storage · BESS · Fort Bend County
Listed as cancelled by ERCOT.
−69 MW

All projects

ProjectFuelMWSubstationStageCOD
Avalon BESSBESS522Tapping the 345 kV Line from Smithers (Bus# 44650) to Bellaire (Bus# 47000).IA Signed12/01/2026
UNICORN BESSBESS279Tap 138 kV Wa Parish (#44015) - Crabb River Road Line (#44170) Line; CNPFIS Requested09/01/2027
Rock Rose BESSBESS20844070 Whaley 345 kVIA Signed03/19/2027
Bypass BESS IIBESS20644000 Wa Parish 345 kVFIS Requested04/30/2028
Elan BESSBESS20342380 Needville 138kVFIS Approved12/31/2026
Crowned Heron BESSBESS154WA Parish 345 kV Bus #44000Sync Approved10/02/2026
Crowned Heron BESS 2BESS154WA Parish 345 kV Bus #44000Sync Approved10/02/2026
Redbird BESSBESS10044090 Cedar Creek 345kVFIS Requested03/01/2029
Elysium Energy Center BESSBESS10044030 Arcola 138 kVScreening01/17/2030
Pato Blanco StorageBESS71Tap 138 kV 44010 W A Parish - 42980 NASH___S02_8FIS Approved12/15/2028
IEP Orchard BESSBESS10Station Name (TDSP Station Code): ORSync Approved12/31/2027
Creekfield SolarSolar161Not listedWithdrawnn/a
Creekfield StorageBESS69Not listedWithdrawnn/a
Fighting Jays BatteryBESS53Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Fort Bend County?
ERCOT's October 2026 report lists 11 active projects in Fort Bend County totalling 2,008 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.