Counties / Texas
Fort Bend County power projects
Fort Bend County, Texas has 11 active power projects totalling 2,008 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 2,008 MW (100%). The largest single project is Avalon BESS (522 MW battery storage). 5 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.
Active projects
11
2.0 GW capacity
IA signed or later
5
45% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
3
since Sep 2026
Changes in Fort Bend County
COD change
10/01/2026
IEP Orchard BESS · BESS · Fort Bend County
Projected COD moved 09/18/2026 → 12/31/2027. Delay #1 for this project.
+15 mo
Withdrawn
09/14/2026
−161 MW
Withdrawn
09/14/2026
−69 MW
All projects
For residents and landowners
- What power projects are planned in Fort Bend County?
- ERCOT's October 2026 report lists 11 active projects in Fort Bend County totalling 2,008 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.