24INR0493 · BESS · Fort Bend County

Crowned Heron BESS 2

Crowned Heron BESS 2 is a 154 MW battery storage project in Fort Bend County, Texas, connecting at WA Parish 345 kV Bus #44000. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 10/02/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0493
Capacity
154 MW
Fuel
BESS (BA)
Interconnecting entity
RWE Renewables
Projected COD
10/02/2026
Entered queue
11/15/2022
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/06/2026
    Energization Approved → Sync Approved
  • 01/27/2026
    IA Signed → Energization Approved
  • 08/20/2024
    FIS Approved → IA Signed
  • 01/28/2024
    FIS Requested → FIS Approved
  • 11/15/2022
    Entered the queue with 154 MW, projected COD 10/02/2026
  • 11/15/2022
    Screening → FIS Requested

Other projects at this substation

Crowned Heron BESSBESS154 MWSync Approved