LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0201 · BESS · Fort Bend County

Rock Rose BESS

Rock Rose BESS is a 208 MW battery storage project in Fort Bend County, Texas, connecting at 44070 Whaley 345 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 03/19/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0201
Capacity
208 MW
Fuel
BESS (BA)
Interconnecting entity
Rock Rose Energy Storage LLC
Projected COD
03/19/2027
Entered queue
09/08/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/18/2026
    FIS Requested → FIS Approved
  • 06/15/2024
    FIS Approved → IA Signed
  • 09/08/2023
    Entered the queue with 208 MW, projected COD 03/19/2027
  • 09/08/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.