ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
22INR0266 · Solar · Fort Bend County

Creekfield Solar

Withdrawn

Creekfield Solar is a 161 MW solar project in Fort Bend County, Texas, with no point of interconnection listed. It is no longer active in ERCOT's interconnection queue.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0266
Capacity
161 MW
Fuel
Solar
Substation
Not listed
Interconnecting entity
Not listed
Projected COD
n/a
Entered queue
09/14/2026
ERCOT zone
n/a
Size category
n/a

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 09/14/2026
    Listed as cancelled

Other projects at this substation

No other projects at this substation.