LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
26INR0375 · BESS · Fort Bend County

Avalon BESS

Avalon BESS is a 522 MW battery storage project in Fort Bend County, Texas, connecting at Tapping the 345 kV Line from Smithers (Bus# 44650) to Bellaire (Bus# 47000).. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/01/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
26INR0375
Capacity
522 MW
Fuel
BESS (BA)
Interconnecting entity
Avalon BESS, LLC
Projected COD
12/01/2026
Entered queue
11/30/2023
ERCOT zone
HOUSTON
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/17/2024
    FIS Approved → IA Signed
  • 05/20/2024
    FIS Requested → FIS Approved
  • 11/30/2023
    Entered the queue with 522 MW, projected COD 12/01/2026
  • 11/30/2023
    Screening → FIS Requested

Other projects at this substation

No other projects at this substation.