Eastland County power projects
Eastland County, Texas has 12 active power projects totalling 1,358 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 891 MW (66%). The largest single project is Damia Solar (306 MW solar). 3 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
12
1.4 GW capacity
IA signed or later
3
25% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Eastland County
COD change
10/01/2026
Silver Star repower · Wind · Eastland County
Projected COD moved 09/05/2026 → 12/31/2026. Delay #1 for this project.
+4 mo
All projects
For residents and landowners
- What power projects are planned in Eastland County?
- ERCOT's October 2026 report lists 12 active projects in Eastland County totalling 1,358 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.