Substation / point of interconnection ยท Eastland County
33285 Rising Star 138 kV
2 active projects totalling 457 MW are queued to connect at 33285 Rising Star 138 kV in Eastland County, Texas, according to ERCOT's October 2026 report.
Active capacity
457 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0274 | Richardson McClung Ranch Solar | Solar | 252 | FIS Requested | 11/30/2029 | 0 |
| 29INR0275 | Richardson McClung Ranch BESS | BESS | 206 | FIS Requested | 11/30/2029 | 0 |