Substation / point of interconnection ยท Eastland County
1642 Flat Creek 138kV
1 active project totalling -7 MW is queued to connect at 1642 Flat Creek 138kV in Eastland County, Texas, according to ERCOT's October 2026 report.
Active capacity
-7 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 18INR0064 | Silver Star repower | Wind | -7 | Sync Approved | 12/31/2026 | 1 |