26INR0603 · Solar · Eastland County
Damia Solar
Damia Solar is a 306 MW solar project in Eastland County, Texas, connecting at Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 07/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0603
- Capacity
- 306 MW
- Fuel
- Solar (PV)
- Substation
- Tap 138kV 6317 Cisco - 3545 MTNBRANCH_8
- County
- Eastland County
- Interconnecting entity
- Damia Solar, LLC
- Projected COD
- 07/01/2028
- Entered queue
- 03/18/2025
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/18/2025Entered the queue with 306 MW, projected COD 07/01/2028
- 03/18/2025Screening → FIS Requested
Other projects at this substation
| Damia Storage | BESS | 153 MW | FIS Requested |