26INR0467 · BESS · Eastland County
Basketflower Storage
Basketflower Storage is a 92 MW battery storage project in Eastland County, Texas, connecting at Tap 138kV Risingstar (285) - Nimrod (289). ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 12/31/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 26INR0467
- Capacity
- 92 MW
- Fuel
- BESS (BA)
- County
- Eastland County
- Interconnecting entity
- Basketflower Solar, LLC
- Projected COD
- 12/31/2027
- Entered queue
- 10/25/2024
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 03/26/2026FIS Requested → FIS Approved
- 10/25/2024Entered the queue with 92 MW, projected COD 12/31/2027
- 10/25/2024Screening → FIS Requested
Other projects at this substation
| Basketflower Solar | Solar | 183 MW | FIS Approved |