Counties / Texas
Mcculloch County power projects
Mcculloch County, Texas has 3 active power projects totalling 751 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 400 MW (53%). The largest single project is Biggs Solar (400 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
3
0.8 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Mcculloch County
COD change
10/01/2026
Biggs Solar · Solar · Mcculloch County
Projected COD moved 11/15/2028 → 06/16/2029. Delay #1 for this project.
+7 mo
COD change
10/01/2026
Biggs BESS · BESS · Mcculloch County
Projected COD moved 11/15/2028 → 06/16/2029. Delay #1 for this project.
+7 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Biggs Solar | Solar | 400 | 76006 Bow Wood 345 kV | FIS Requested | 06/16/2029 |
| Biggs BESS | BESS | 200 | 76006 Bow Wood 345 kV | FIS Requested | 06/16/2029 |
| Pecan Ridge | BESS | 151 | 60386 HEARTLAN2A 69kV | FIS Requested | 06/30/2027 |
For residents and landowners
- What power projects are planned in Mcculloch County?
- ERCOT's October 2026 report lists 3 active projects in Mcculloch County totalling 751 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.