LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Mcculloch County power projects

Mcculloch County, Texas has 3 active power projects totalling 751 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 400 MW (53%). The largest single project is Biggs Solar (400 MW solar). 0 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
3
0.8 GW capacity
IA signed or later
0
0% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Mcculloch County

COD change
10/01/2026
Biggs Solar · Solar · Mcculloch County
Projected COD moved 11/15/2028 → 06/16/2029. Delay #1 for this project.
+7 mo
COD change
10/01/2026
Biggs BESS · BESS · Mcculloch County
Projected COD moved 11/15/2028 → 06/16/2029. Delay #1 for this project.
+7 mo

All projects

ProjectFuelMWSubstationStageCOD
Biggs SolarSolar40076006 Bow Wood 345 kVFIS Requested06/16/2029
Biggs BESSBESS20076006 Bow Wood 345 kVFIS Requested06/16/2029
Pecan RidgeBESS15160386 HEARTLAN2A 69kVFIS Requested06/30/2027

For residents and landowners

What power projects are planned in Mcculloch County?
ERCOT's October 2026 report lists 3 active projects in Mcculloch County totalling 751 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.