Substation / point of interconnection ยท Mcculloch County
76006 Bow Wood 345 kV
2 active projects totalling 600 MW are queued to connect at 76006 Bow Wood 345 kV in Mcculloch County, Texas, according to ERCOT's October 2026 report.
Active capacity
600 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0111 | Biggs Solar | Solar | 400 | FIS Requested | 06/16/2029 | 1 |
| 28INR0110 | Biggs BESS | BESS | 200 | FIS Requested | 06/16/2029 | 1 |