28INR0111 · Solar · Mcculloch County

Biggs Solar

COD delayed 1×

Biggs Solar is a 400 MW solar project in Mcculloch County, Texas, connecting at 76006 Bow Wood 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/16/2029. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0111
Capacity
400 MW
Fuel
Solar (PV)
Interconnecting entity
Biggs Solar Farm, LLC
Projected COD
06/16/2029
Entered queue
07/22/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 11/15/2028 → 06/16/2029 (+7 months)
  • 04/21/2025
    Screening → FIS Requested
  • 07/22/2024
    Entered the queue with 400 MW, projected COD 11/15/2028

Other projects at this substation

Biggs BESSBESS200 MWFIS Requested