28INR0110 · BESS · Mcculloch County
Biggs BESS
COD delayed 1×
Biggs BESS is a 200 MW battery storage project in Mcculloch County, Texas, connecting at 76006 Bow Wood 345 kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/16/2029. Its projected COD has been pushed back 1 time in the reports compared.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 28INR0110
- Capacity
- 200 MW
- Fuel
- BESS (BA)
- Substation
- 76006 Bow Wood 345 kV
- County
- Mcculloch County
- Interconnecting entity
- Biggs Battery Facility, LLC
- Projected COD
- 06/16/2029
- Entered queue
- 07/22/2024
- ERCOT zone
- SOUTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Projected COD moved 11/15/2028 → 06/16/2029 (+7 months)
- 04/21/2025Screening → FIS Requested
- 07/22/2024Entered the queue with 200 MW, projected COD 11/15/2028
Other projects at this substation
| Biggs Solar | Solar | 400 MW | FIS Requested |