Counties / Texas
Limestone County power projects
Limestone County, Texas has 9 active power projects totalling 1,063 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 857 MW (81%). The largest single project is Varadero Solar (206 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.
Active projects
9
1.1 GW capacity
IA signed or later
4
44% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Limestone County
COD change
10/01/2026
Naduah Solar · Solar · Limestone County
Projected COD moved 10/15/2027 → 04/15/2028. Delay #1 for this project.
+6 mo
Stage change
09/17/2026
FIS Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Varadero Solar | Solar | 206 | #68092 Liberty Station 345kV | IA Signed | 04/01/2029 |
| Fewell Solar | Solar | 204 | Tap 138kV 3597 Groesbeck - 3634 Groesbeck Main | IA Signed | 05/15/2028 |
| Leighton Solar | Solar | 181 | 98 Fernleaf 138 kV | IA Signed | 12/06/2027 |
| Bonham Solar SLF | Solar | 138 | TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634 | IA Signed | 04/06/2027 |
| Bonham Storage SLF | BESS | 105 | Tap 138kV 3632 Mexia_Main - 3634 Groesbeck_Main | FIS Approved | 07/01/2027 |
| Naduah Solar | Solar | 78 | Tap 69kV Ben Hur (99) - Prairie Hill (107) | FIS Requested | 04/15/2028 |
| Findley BESS | BESS | 52 | Tap 69kV #107 Prairie Hill - #99 Ben Hur | FIS Approved | 01/01/2028 |
| Findley Solar | Solar | 50 | Tap 69kV #107 Prairie Hill - #99 Ben Hur | FIS Requested | 01/01/2028 |
| Chariot Storage | BESS | 50 | tap 69kV 99 Ben Hur - 107 Prairie Hill | FIS Requested | 02/29/2028 |
| Tehuacana Wind | Wind | 600 | Not listed | Withdrawn | n/a |
| Fiji Solar | Solar | 203 | Not listed | Withdrawn | n/a |
| Diver Energy Storage SLF | BESS | 0 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Limestone County?
- ERCOT's October 2026 report lists 9 active projects in Limestone County totalling 1,063 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.