25INR0021 · Solar · Limestone County
Findley Solar
Findley Solar is a 50 MW solar project in Limestone County, Texas, connecting at Tap 69kV #107 Prairie Hill - #99 Ben Hur. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 01/01/2028.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 25INR0021
- Capacity
- 50 MW
- Fuel
- Solar (PV)
- Substation
- Tap 69kV #107 Prairie Hill - #99 Ben Hur
- County
- Limestone County
- Interconnecting entity
- Adon Texas Sixteen LLC
- Projected COD
- 01/01/2028
- Entered queue
- 10/05/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/24/2022Screening → FIS Requested
- 10/05/2021Entered the queue with 50 MW, projected COD 01/01/2028
Other projects at this substation
| Findley BESS | BESS | 52 MW | FIS Approved |