LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
28INR0048 · BESS · Limestone County

Findley BESS

Findley BESS is a 52 MW battery storage project in Limestone County, Texas, connecting at Tap 69kV #107 Prairie Hill - #99 Ben Hur. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 01/01/2028.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
28INR0048
Capacity
52 MW
Fuel
BESS (BA)
Interconnecting entity
Adon Texas Sixteen LLC
Projected COD
01/01/2028
Entered queue
01/16/2024
ERCOT zone
NORTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 01/21/2026
    FIS Requested → FIS Approved
  • 01/16/2024
    Entered the queue with 52 MW, projected COD 01/01/2028
  • 01/16/2024
    Screening → FIS Requested

Other projects at this substation

Findley SolarSolar50 MWFIS Requested