Substation / point of interconnection ยท Limestone County

TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634

1 active project totalling 138 MW is queued to connect at TAP 138 kV MEXIA_2_1_8 3632 - GROES_SE1_8 3634 in Limestone County, Texas, according to ERCOT's October 2026 report.

Active capacity
138 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0199Bonham Solar SLFSolar138IA Signed04/06/20270