Glasscock County power projects

Glasscock County, Texas has 18 active power projects totalling 3,409 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,059 MW (31%). The largest single project is Proteus London-Leigh Solar SLF (600 MW solar). 11 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
18
3.4 GW capacity
IA signed or later
11
61% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
2
since Sep 2026

Changes in Glasscock County

COD change
10/01/2026
Gardner Draw Solar · Solar · Glasscock County
Projected COD moved 12/31/2027 → 06/01/2028. Delay #1 for this project.
+5 mo
Stage change
09/16/2026
Gardner Draw Solar · Solar · Glasscock County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

ProjectFuelMWSubstationStageCOD
Proteus London-Leigh Solar SLFSolar600345kV Bernoulli (bus # 59907)FIS Requested09/30/2028
Indigo Quill GasGas37059902 Sand Bluff 345kVFIS Requested12/29/2028
Gardner Draw SolarSolar31059902 Sand Bluff 345kVIA Signed06/01/2028
Gusty WindpowerWind249Tap 345kV 59903 Bearkat - 1058 Longshore_5; Anemone 345 kV StationIA Signed12/31/2028
Windjammer WindpowerWind244tap 345kV 59902 Sand Bluff Wind Farm - 59907 BernoulliIA Signed12/31/2028
Pleiades StorageBESS206Tap 138kV Einstein 23852 - 10043 St. LawrenceFIS Approved09/22/2029
Champaign BESSBESS201Tap 138kV Shaw POD (18664) – Desert Wind Sub (11283)IA Signed03/31/2028
Cummins BESSBESS2011333 MCDONALD 138kVFIS Requested06/30/2028
Feather Dalea BESSBESS20059902 Sand Bluff 345kVFIS Requested07/02/2027
Honey Mesquite Wind FarmWind17459902 Sand Bluff 345kVSync Approved12/30/2026
Harald (BearKat Wind B)Wind16259903 Bearkat 345kVSync Approved12/03/2026
Cannibal Draw SolarSolar150Sand_Bluff 345 kV (59902)IA Signed04/10/2028
Forest Creek Wind RepowerWind125Mcdonald 138 kV (Bus #: 1333)Sync Approved12/31/2026
Sagewood BESSBESS101tap McDonald Road Switch (1333) – Pastores Switch (10121) ckt 1FIS Requested03/31/2028
Cannibal Draw StorageBESS99Sand_Bluff 345 kV (59902)IA Signed04/10/2028
Panther Creek 1 RepowerWind111058 Longshore 345kVSync Approved12/31/2026
Panther Creek 2 RepowerWind8Longshore 345kV [Bus# 1058]Sync Approved12/31/2026
Proteus London-Leigh Storage SLFBESS0Bernoulli (bus # 59907)FIS Requested09/30/2028
Kontiki 1 Wind (ERIK)Wind250Not listedWithdrawnn/a
Kontiki 2 Wind (ERNEST)Wind250Not listedWithdrawnn/a
Lacy Creek Energy Storage SLFBESS0Not listedWithdrawnn/a

For residents and landowners

What power projects are planned in Glasscock County?
ERCOT's October 2026 report lists 18 active projects in Glasscock County totalling 3,409 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.