Substation / point of interconnection ยท Glasscock County
345kV Bernoulli (bus # 59907)
1 active project totalling 600 MW is queued to connect at 345kV Bernoulli (bus # 59907) in Glasscock County, Texas, according to ERCOT's October 2026 report.
Active capacity
600 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0608 | Proteus London-Leigh Solar SLF | Solar | 600 | FIS Requested | 09/30/2028 | 0 |