Substation / point of interconnection ยท Glasscock County

59902 Sand Bluff 345kV

4 active projects totalling 1,054 MW are queued to connect at 59902 Sand Bluff 345kV in Glasscock County, Texas, according to ERCOT's October 2026 report.

Active capacity
1,054 MW
queued at this substation
Active projects
4
4 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
30INR0080Indigo Quill GasGas370FIS Requested12/29/20280
27INR0355Gardner Draw SolarSolar310IA Signed06/01/20281
27INR0371Feather Dalea BESSBESS200FIS Requested07/02/20270
26INR0447Honey Mesquite Wind FarmWind174Sync Approved12/30/20260