ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0578 · Wind · Glasscock County

Panther Creek 1 Repower

Panther Creek 1 Repower is a 11 MW wind project in Glasscock County, Texas, connecting at 1058 Longshore 345kV. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 12/31/2026.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0578
Capacity
11 MW
Fuel
Wind (WT)
Interconnecting entity
Panther Creek Wind Farm I&II, LLC
Projected COD
12/31/2026
Entered queue
06/21/2023
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/02/2024
    FIS Approved → Sync Approved
  • 05/03/2024
    FIS Requested → FIS Approved
  • 06/21/2023
    Entered the queue with 11 MW, projected COD 12/31/2026
  • 06/21/2023
    Screening → FIS Requested