ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Fisher County power projects

Fisher County, Texas has 13 active power projects totalling 6,384 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 3,000 MW (47%). The largest single project is Brazos Energy Security (3,000 MW natural gas). 6 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.

Active projects
13
6.4 GW capacity
IA signed or later
6
46% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Fisher County

New
10/01/2026
Brazos Energy Security · Gas · Fisher County
Entered the queue at Tap 345 kV (Bus #1048) Tonkawa Switch – (Bus #11050) Dusty Road. Projected COD 09/22/2030.
+3,000 MW
New
10/01/2026
Rugged Prairie Wind · Wind · Fisher County
Entered the queue at Tap 345kV BUS #11305 Dermott- BUS #60706 Kirchhef. Projected COD 12/01/2029.
+294 MW
Stage change
09/18/2026
Rugged Prairie Wind · Wind · Fisher County
Moved from Screening to FIS Requested.
FIS Requested
Stage change
09/16/2026
Brazos Energy Security · Gas · Fisher County
Moved from Screening to FIS Requested.
FIS Requested

All projects

For residents and landowners

What power projects are planned in Fisher County?
ERCOT's October 2026 report lists 13 active projects in Fisher County totalling 6,384 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.