LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
24INR0496 · BESS · Fisher County

Indigo Storage

Indigo Storage is a 60 MW battery storage project in Fisher County, Texas, connecting at tap 345 kV 68001 Claytonville – 68004 Phantom Hill Circuit 2. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 09/17/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
24INR0496
Capacity
60 MW
Fuel
BESS (BA)
Interconnecting entity
Innovative Solar 245, LLC
Projected COD
09/17/2027
Entered queue
12/15/2022
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 03/27/2026
    FIS Requested → IA Signed
  • 08/28/2023
    Screening → FIS Requested
  • 12/15/2022
    Entered the queue with 60 MW, projected COD 09/17/2027

Other projects at this substation

Indigo SolarSolar150 MWIA Signed
Indigo Storage 2BESS60 MWIA Signed
Indigo Storage 3BESS60 MWIA Signed
Indigo Storage 4BESS60 MWIA Signed