25INR0632 · Solar · Fisher County

Jenna Eco-Electric Solar

Jenna Eco-Electric Solar is a 576 MW solar project in Fisher County, Texas, connecting at Tap 345 kV 1048 Tonkawa Switch - 1430 Graham SES. ERCOT's October 2026 report shows it at the FIS Approved stage with a projected commercial operation date of 04/16/2029.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0632
Capacity
576 MW
Fuel
Solar (PV)
Interconnecting entity
Clean Energy Holdings, LLC
Projected COD
04/16/2029
Entered queue
05/17/2024
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/02/2026
    FIS Requested → FIS Approved
  • 05/17/2024
    Entered the queue with 576 MW, projected COD 04/16/2029
  • 05/17/2024
    Screening → FIS Requested

Other projects at this substation