Substation / point of interconnection ยท Fisher County
Tap 345 kV 1048 Tonkawa Switch - 1430 Graham SES
1 active project totalling 576 MW is queued to connect at Tap 345 kV 1048 Tonkawa Switch - 1430 Graham SES in Fisher County, Texas, according to ERCOT's October 2026 report.
Active capacity
576 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 25INR0632 | Jenna Eco-Electric Solar | Solar | 576 | FIS Approved | 04/16/2029 | 0 |