Crane County power projects
Crane County, Texas has 12 active power projects totalling 2,740 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 1,370 MW (50%). The largest single project is Western Flats Storage (411 MW battery storage). 5 projects have signed an interconnection agreement or reached a later stage. 2 projects in the county are listed as withdrawn or cancelled.
Active projects
12
2.7 GW capacity
IA signed or later
5
42% of active projects
Withdrawn or cancelled
2
listed by ERCOT
Changes tracked
4
since Sep 2026
Changes in Crane County
Withdrawn
Unconfirmed
10/01/2026
Soda Lake BESS 1 · BESS · Crane County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−204 MW
COD change
10/01/2026
Cattle Drive Solar · Solar · Crane County
Projected COD moved 03/21/2029 → 12/31/2028. Moved earlier.
-3 mo
COD change
10/01/2026
BRP Pictor BESS · BESS · Crane County
Projected COD moved 11/01/2025 → 12/31/2029. Delay #1 for this project.
+50 mo
COD change
10/01/2026
Fowler Ranch Storage · BESS · Crane County
Projected COD moved 06/30/2027 → 09/30/2027. Delay #1 for this project.
+3 mo
All projects
For residents and landowners
- What power projects are planned in Crane County?
- ERCOT's October 2026 report lists 12 active projects in Crane County totalling 2,740 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.