Substation / point of interconnection ยท Crane County
76000 North McCamey 345kV
1 active project totalling 307 MW is queued to connect at 76000 North McCamey 345kV in Crane County, Texas, according to ERCOT's October 2026 report.
Active capacity
307 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 29INR0013 | Cattle Drive Solar | Solar | 307 | IA Signed | 12/31/2028 | 0 |