LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Crane County

138 kV Soda Lake (#76026)

4 active projects totalling 814 MW are queued to connect at 138 kV Soda Lake (#76026) in Crane County, Texas, according to ERCOT's October 2026 report.

Active capacity
814 MW
queued at this substation
Active projects
4
4 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
24INR0383Soda Lake BESS 2 SLFBESS205IA Signed10/30/20280
28INR0389Tri-X BESS 1 SLFBESS205IA Signed10/30/20280
23INR0080Soda Lake Solar 2 SLFSolar202IA Signed10/30/20280
20INR0143Tri-X Solar 1 SLFSolar202IA Signed10/30/20280