23INR0501 · BESS · Crane County
Soda Lake BESS 1
Withdrawn
Soda Lake BESS 1 is a 204 MW battery storage project in Crane County, Texas, connecting at 138kV Soda Lake Substation (#76026). It is no longer active in ERCOT's interconnection queue.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0501
- Capacity
- 204 MW
- Fuel
- BESS (BA)
- Substation
- 138kV Soda Lake Substation (#76026)
- County
- Crane County
- Interconnecting entity
- Mendoza Trail BESS, LLC
- Projected COD
- 08/15/2026
- Entered queue
- 08/20/2018
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Listed as withdrawn UNCONFIRMED
- 11/05/2025Energization Approved → Sync Approved
- 09/02/2025IA Signed → Energization Approved
- 10/22/2024FIS Requested → FIS Approved
- 08/09/2022Screening → FIS Requested
- 08/20/2018Entered the queue with 204 MW, projected COD 08/15/2026
- 08/20/2018FIS Approved → IA Signed
Other projects at this substation
No other projects at this substation.