Counties / Texas
Callahan County power projects
Callahan County, Texas has 5 active power projects totalling 1,571 MW in ERCOT's interconnection queue as of the October 2026 report. Solar is the largest share at 820 MW (52%). The largest single project is Sequoia II Solar (418 MW solar). 2 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
5
1.6 GW capacity
IA signed or later
2
40% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
1
since Sep 2026
Changes in Callahan County
COD change
10/01/2026
Sequoia II Solar · Solar · Callahan County
Projected COD moved 11/21/2026 → 01/28/2027. Delay #1 for this project.
+2 mo
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Sequoia II Solar | Solar | 418 | 68051 Reata 345kV | IA Signed | 01/28/2027 |
| Hittson Creek Solar | Solar | 403 | Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051). | FIS Requested | 12/15/2028 |
| Baird North Wind | Wind | 340 | 68008 Latimer 345kV | Sync Approved | 12/31/2026 |
| Hittson Creek BESS | BESS | 205 | Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051). | FIS Requested | 12/15/2028 |
| Guitar BESS | BESS | 205 | Tap 138kV 6275 ABEAST4A - 6670 PUTN4C | FIS Requested | 12/31/2027 |
For residents and landowners
- What power projects are planned in Callahan County?
- ERCOT's October 2026 report lists 5 active projects in Callahan County totalling 1,571 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.