Substation / point of interconnection ยท Callahan County
Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051).
2 active projects totalling 608 MW are queued to connect at Tapping the two 345 kV Lines: Sam Line Reactor (Bus# 68005) - Reata (Bus# 68051) and Latimer (Bus# 68008) - Reata (Bus# 68051). in Callahan County, Texas, according to ERCOT's October 2026 report.
Active capacity
608 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 28INR0245 | Hittson Creek Solar | Solar | 403 | FIS Requested | 12/15/2028 | 0 |
| 28INR0246 | Hittson Creek BESS | BESS | 205 | FIS Requested | 12/15/2028 | 0 |