22INR0262 · Solar · Callahan County

Sequoia II Solar

COD delayed 1×

Sequoia II Solar is a 418 MW solar project in Callahan County, Texas, connecting at 68051 Reata 345kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 01/28/2027. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
22INR0262
Capacity
418 MW
Fuel
Solar (PV)
Interconnecting entity
ENBRIDGE SOLAR SEQUOIA II LLC
Projected COD
01/28/2027
Entered queue
01/22/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 11/21/2026 → 01/28/2027 (+2 months)
  • 03/16/2026
    FIS Requested → FIS Approved
  • 08/29/2023
    FIS Approved → IA Signed
  • 08/27/2020
    Screening → FIS Requested
  • 01/22/2020
    Entered the queue with 418 MW, projected COD 11/21/2026

Other projects at this substation

No other projects at this substation.