Substation / point of interconnection ยท Callahan County
68008 Latimer 345kV
1 active project totalling 340 MW is queued to connect at 68008 Latimer 345kV in Callahan County, Texas, according to ERCOT's October 2026 report.
Active capacity
340 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 20INR0083 | Baird North Wind | Wind | 340 | Sync Approved | 12/31/2026 | 0 |