LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Counties / Texas

Bastrop County power projects

Bastrop County, Texas has 12 active power projects totalling 4,815 MW in ERCOT's interconnection queue as of the October 2026 report. Natural gas is the largest share at 3,822 MW (79%). The largest single project is Bastrop Peaking Generators (TEF-Due Diligence) (1,104 MW natural gas). 8 projects have signed an interconnection agreement or reached a later stage. 3 projects in the county are listed as withdrawn or cancelled.

Active projects
12
4.8 GW capacity
IA signed or later
8
67% of active projects
Withdrawn or cancelled
3
listed by ERCOT
Changes tracked
4
since Sep 2026

Changes in Bastrop County

Withdrawn
Unconfirmed
10/01/2026
Big Star Solar · Solar · Bastrop County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−203 MW
Withdrawn
Unconfirmed
10/01/2026
Big Star Storage · BESS · Bastrop County
Missing from the latest report, not yet marked withdrawn by ERCOT.
−80 MW
COD change
10/01/2026
Waterloo BESS 1 · BESS · Bastrop County
Projected COD moved 12/01/2027 → 12/15/2028. Delay #1 for this project.
+12 mo
Stage change
09/18/2026
Waterloo Solar 1 · Solar · Bastrop County
Moved from FIS Requested to FIS Approved.
FIS Approved

All projects

For residents and landowners

What power projects are planned in Bastrop County?
ERCOT's October 2026 report lists 12 active projects in Bastrop County totalling 4,815 MW. The table on this page lists each one with its fuel type, size, substation and stage.
Where do these projects connect to the grid?
Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
What does "IA Signed" mean?
The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
When would construction start?
Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
Does a project in the queue mean it will be built?
No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.