25INR0447 · BESS · Bastrop County

Waterloo BESS 1

COD delayed 1×

Waterloo BESS 1 is a 120 MW battery storage project in Bastrop County, Texas, connecting at Tap 345-kV 7040 Austrop to 7042 Zorn. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 12/15/2028. Its projected COD has been pushed back 1 time in the reports compared.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
25INR0447
Capacity
120 MW
Fuel
BESS (BA)
Interconnecting entity
Waterloo BESS, LLC
Projected COD
12/15/2028
Entered queue
05/03/2023
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 10/01/2026
    Projected COD moved 12/01/2027 → 12/15/2028 (+12 months)
  • 09/04/2024
    FIS Requested → IA Signed
  • 05/03/2023
    Entered the queue with 120 MW, projected COD 12/01/2027
  • 05/03/2023
    Screening → FIS Requested

Other projects at this substation

Waterloo Solar 1Solar201 MWIA Signed