31INR0011 · Gas · Bastrop County

SIM GIDEON GAS RICE

SIM GIDEON GAS RICE is a 226 MW natural gas project in Bastrop County, Texas, connecting at (#7310) SIM GIDEON 138 kV. ERCOT's October 2026 report shows it at the IA Signed stage with a projected commercial operation date of 05/10/2031.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
31INR0011
Capacity
226 MW
Fuel
Gas (IC)
Interconnecting entity
LCRA
Projected COD
05/10/2031
Entered queue
07/08/2025
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 12/19/2025
    FIS Requested → IA Signed
  • 07/08/2025
    Entered the queue with 226 MW, projected COD 05/10/2031
  • 07/08/2025
    Screening → FIS Requested

Other projects at this substation

Sim Gideon Combined CycleGas880 MWIA Signed