Substation / point of interconnection ยท Bastrop County
7048 L_GARFIE5_1Y 345kV
1 active project totalling 1,104 MW is queued to connect at 7048 L_GARFIE5_1Y 345kV in Bastrop County, Texas, according to ERCOT's October 2026 report.
Active capacity
1,104 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 26INR0261 | Bastrop Peaking Generators (TEF-Due Diligence) | Gas | 1,104 | IA Signed | 12/07/2027 | 0 |