Winkler County power projects
Winkler County, Texas has 3 active power projects totalling 623 MW in ERCOT's interconnection queue as of the October 2026 report. Wind is the largest share at 407 MW (65%). The largest single project is Horizon Ridge Wind (407 MW wind). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
3
0.6 GW capacity
IA signed or later
1
33% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Winkler County
New
10/01/2026
Horizon Ridge Wind · Wind · Winkler County
Entered the queue at POIB is 131853 NOTSW_1_8 - the Notrees SW Substation - Project includes property in Ector, Andrews, and Winkler counties.. Projected COD 04/23/2030.
+407 MW
Stage change
09/03/2026
FIS Requested
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Horizon Ridge Wind | Wind | 407 | POIB is 131853 NOTSW_1_8 - the Notrees SW Substation - Project includes property in Ector, Andrews, and Winkler counties. | FIS Requested | 04/23/2030 |
| BRP Volans BESS | BESS | 207 | 11189 Quarry Field SW - 1074 Wink 138kV | FIS Requested | 12/01/2027 |
| Coyanosa Gas | Gas | 10 | COYANOSA | IA Signed | 12/17/2026 |
| Bestla Solar | Solar | 180 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Winkler County?
- ERCOT's October 2026 report lists 3 active projects in Winkler County totalling 623 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.