BRP Volans BESS

BRP Volans BESS is a 207 MW battery storage project in Winkler County, Texas, connecting at 11189 Quarry Field SW - 1074 Wink 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
23INR0071
Capacity
207 MW
Fuel
BESS (BA)
Interconnecting entity
BRP Volans BESS LLC
Projected COD
12/01/2027
Entered queue
08/04/2020
ERCOT zone
WEST
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 08/24/2020
    Screening → FIS Requested
  • 08/04/2020
    Entered the queue with 207 MW, projected COD 12/01/2027