23INR0071 · BESS · Winkler County
BRP Volans BESS
BRP Volans BESS is a 207 MW battery storage project in Winkler County, Texas, connecting at 11189 Quarry Field SW - 1074 Wink 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 12/01/2027.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0071
- Capacity
- 207 MW
- Fuel
- BESS (BA)
- Substation
- 11189 Quarry Field SW - 1074 Wink 138kV
- County
- Winkler County
- Interconnecting entity
- BRP Volans BESS LLC
- Projected COD
- 12/01/2027
- Entered queue
- 08/04/2020
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 08/24/2020Screening → FIS Requested
- 08/04/2020Entered the queue with 207 MW, projected COD 12/01/2027