30INR0128 · Wind · Winkler County
Horizon Ridge Wind
Horizon Ridge Wind is a 407 MW wind project in Winkler County, Texas, connecting at POIB is 131853 NOTSW_1_8 - the Notrees SW Substation - Project includes property in Ector, Andrews, and Winkler counties.. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 04/23/2030.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 30INR0128
- Capacity
- 407 MW
- Fuel
- Wind (WT)
- County
- Winkler County
- Interconnecting entity
- CPV Horizon Ridge Wind, LLC
- Projected COD
- 04/23/2030
- Entered queue
- 09/03/2026
- ERCOT zone
- WEST
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 10/01/2026Entered the queue with 407 MW, projected COD 04/23/2030
- 09/03/2026Screening → FIS Requested
Other projects at this substation
No other projects at this substation.