Counties / Texas
Rusk County power projects
Rusk County, Texas has 5 active power projects totalling 940 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 511 MW (54%). The largest single project is Brantley Branch Batt (302 MW battery storage). 1 project has signed an interconnection agreement or reached a later stage. 1 project in the county is listed as withdrawn or cancelled.
Active projects
5
0.9 GW capacity
IA signed or later
1
20% of active projects
Withdrawn or cancelled
1
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Rusk County
MW change
10/01/2026
202 → 201 MW
Stage change
09/15/2026
FIS Approved
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Brantley Branch Batt | BESS | 302 | Mt. Enterprise (Bus # 3116) – Martin Lake 345kv Line (Bus # 3100 | FIS Requested | 02/01/2029 |
| Zeus Rusk BESS | BESS | 209 | Tap 345kV 3109 Stryker to 3100 Martin Lake | FIS Requested | 09/01/2027 |
| Dry Creek Solar II | Solar | 201 | Dorsett 345 kV Switching Station(tap 345 kV 3100 Martin Lake - 3105 Elkton) | FIS Approved | 02/01/2028 |
| Dry Creek Solar I | Solar | 201 | tap 345kV 3100 Martin Lake - 3105 Elkton | Sync Approved | 01/31/2026 |
| Zeus Rusk Solar | Solar | 27 | Tap 345kV 3109 Stryker to 3100 Martin Lake | FIS Requested | 09/01/2027 |
| Railway BESS | BESS | 255 | Not listed | Withdrawn | n/a |
For residents and landowners
- What power projects are planned in Rusk County?
- ERCOT's October 2026 report lists 5 active projects in Rusk County totalling 940 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.