23INR0286 · Solar · Rusk County
Dry Creek Solar I
Dry Creek Solar I is a 201 MW solar project in Rusk County, Texas, connecting at tap 345kV 3100 Martin Lake - 3105 Elkton. ERCOT's October 2026 report shows it at the Sync Approved stage with a projected commercial operation date of 01/31/2026.
ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved
Key facts
- INR
- 23INR0286
- Capacity
- 201 MW
- Fuel
- Solar (PV)
- Substation
- tap 345kV 3100 Martin Lake - 3105 Elkton
- County
- Rusk County
- Interconnecting entity
- OAK HILL SOLAR LLC
- Projected COD
- 01/31/2026
- Entered queue
- 08/18/2021
- ERCOT zone
- NORTH
- Size category
- Large
Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page
History
- 05/19/2025Energization Approved → Sync Approved
- 05/08/2025IA Signed → Energization Approved
- 06/12/2024FIS Requested → FIS Approved
- 11/02/2023FIS Approved → IA Signed
- 03/30/2022Screening → FIS Requested
- 08/18/2021Entered the queue with 201 MW, projected COD 01/31/2026
Other projects at this substation
No other projects at this substation.