ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
Substation / point of interconnection ยท Rusk County

Tap 345kV 3109 Stryker to 3100 Martin Lake

2 active projects totalling 236 MW are queued to connect at Tap 345kV 3109 Stryker to 3100 Martin Lake in Rusk County, Texas, according to ERCOT's October 2026 report.

Active capacity
236 MW
queued at this substation
Active projects
2
2 projects ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
345 kV
read from the name

Projects at this substation

INRProjectFuelMWStageCODDelays
25INR0591Zeus Rusk BESSBESS209FIS Requested09/01/20270
25INR0590Zeus Rusk SolarSolar27FIS Requested09/01/20270