Maverick County power projects
Maverick County, Texas has 7 active power projects totalling 1,498 MW in ERCOT's interconnection queue as of the October 2026 report. Battery storage is the largest share at 988 MW (66%). The largest single project is Senator Aggreko Solar (259 MW solar). 4 projects have signed an interconnection agreement or reached a later stage. 0 projects in the county are listed as withdrawn or cancelled.
Active projects
7
1.5 GW capacity
IA signed or later
4
57% of active projects
Withdrawn or cancelled
0
listed by ERCOT
Changes tracked
2
since Sep 2026
Changes in Maverick County
MW change
10/01/2026
251 → 259 MW
MW change
10/01/2026
153 → 148 MW
All projects
| Project | Fuel | MW | Substation | Stage | COD |
|---|---|---|---|---|---|
| Senator Aggreko Solar | Solar | 259 | 138 kV Sunglow Substation (#78016) | IA Signed | 03/31/2029 |
| Sugaree Solar | Solar | 251 | 138kV Escondido (8260) to Brackettville (8252) | IA Signed | 09/21/2028 |
| Althea Storage | BESS | 251 | Tap Escondido (8260) - Brackettville (8252) | IA Signed | 09/21/2028 |
| Old Victory Energy Center | BESS | 202 | 8692 MAVERICK4A 138kV | FIS Requested | 06/01/2030 |
| De Los Santos | BESS | 201 | 78016 Sunglow Substation 138kV | FIS Requested | 12/01/2027 |
| Serrano Storage | BESS | 186 | 8267 GANSO Substation 138kV | FIS Requested | 12/01/2027 |
| Senator Aggreko Storage | BESS | 148 | 138 kV Sunglow Substation (#78016) | IA Signed | 03/31/2029 |
For residents and landowners
- What power projects are planned in Maverick County?
- ERCOT's October 2026 report lists 7 active projects in Maverick County totalling 1,498 MW. The table on this page lists each one with its fuel type, size, substation and stage.
- Where do these projects connect to the grid?
- Each project names a point of interconnection, usually a substation or a tap on a transmission line. Land near those points is where developers look for sites.
- What does "IA Signed" mean?
- The developer has signed an interconnection agreement with the transmission owner. It is one of the strongest signs in the queue that a project may be built, though projects can still withdraw.
- When would construction start?
- Usually 12 to 24 months before the projected commercial operation date (COD). CODs often move later; each project page shows how many times its COD has changed.
- Does a project in the queue mean it will be built?
- No. Many queued projects are never built. The queue shows requests to connect, not approved construction. County permits, tax agreements and financing are separate steps.