LoneStarGrid
ERCOT GIS report of 10/01/2026 2 monthly reports compared Next update after ERCOT's next monthly report
27INR0253 · BESS · Maverick County

Old Victory Energy Center

Old Victory Energy Center is a 202 MW battery storage project in Maverick County, Texas, connecting at 8692 MAVERICK4A 138kV. ERCOT's October 2026 report shows it at the FIS Requested stage with a projected commercial operation date of 06/01/2030.

ScreeningFIS RequestedFIS ApprovedIA SignedEnergization ApprovedSync Approved

Key facts

INR
27INR0253
Capacity
202 MW
Fuel
BESS (BA)
Interconnecting entity
Nova Clean Energy LLC
Projected COD
06/01/2030
Entered queue
04/25/2024
ERCOT zone
SOUTH
Size category
Large

Source: ERCOT Generation Interconnection Status report, October 2026. ERCOT report page

History

  • 04/25/2024
    Entered the queue with 202 MW, projected COD 06/01/2030
  • 04/25/2024
    Screening → FIS Requested

Other projects at this substation