Substation / point of interconnection ยท Maverick County
8267 GANSO Substation 138kV
1 active project totalling 186 MW is queued to connect at 8267 GANSO Substation 138kV in Maverick County, Texas, according to ERCOT's October 2026 report.
Active capacity
186 MW
queued at this substation
Active projects
1
1 project ever listed
Withdrawn share EST
0%
of projects listed here
Voltage
138 kV
read from the name
Projects at this substation
| INR | Project | Fuel | MW | Stage | COD | Delays |
|---|---|---|---|---|---|---|
| 24INR0617 | Serrano Storage | BESS | 186 | FIS Requested | 12/01/2027 | 0 |